[GxP Add-on] Completion and Log Out

Hello Everyone,

My post is relevant if you’re using Version: LTS 5.1 with GxP Add-on

With GxP Add-on: Log out = App canceled

Which means that if you use the trigger Complete Then Log out Current User you will be reporting one completion and one cancellation of the app.

First it’s taking some time to report 2 completion data. Second it’s confusing the user to see the pop-up message app canceled (it looks like they did something wrong). Third it’s not possible to isolate the app cancellation from a user log out from inactivity and a user log out from a button designed on purpose.

At this point, I don’t have the perfect solution so I’m opening the discussion to find a solution with everyone :handshake: